| JMT is preparing designs, drawings and bid documents for three submersible wastewater pump stations for the Double Run Wastewater Collection System. Project features include: Pumps ranging from 80 to 1,450 gallons per minute (gpm) Approximately 4,300 feet of 4-inch force main piping 7,800 feet of 8-inch force main piping 19,250 feet of 14-inch force main piping 17,350 feet of 10-inch and 12-inch gravity collection and interceptor sewer piping Preparing a generic standard design, drawings and specifications for submersible pump stations, which will be used for design of future projects. Interfaced with multiple residential land developers for new interceptor and pump station force main piping alignment study/verification, as required to establish the necessary new infrastructure for both new and existing development in this portion of the County A separate task includes preparing designs, drawings and bid documents for approximately 55,050 feet of new 24-inch force main to serve as a bypass to the existing trunk manifold force main during high wastewater flow events.
| | 
| |
|